Decommissioning Nuclear Plants Costing Billion$ More Than Expected

This article takes a look at cost estimates of nuclear power plant decommissioning from the 1980s, and how widely inaccurate they turned out to be. This is a pretty fascinating look at past articles in the Bulletin of the Atomic Scientists that consistently downplayed the costs of decommissioning, for example: 'The Yankee Nuclear Power Station in Rowe, Massachusetts, took 15 years to decommission—or five times longer than was needed to build it. And decommissioning the plant—constructed early in the 1960s for $39 million—cost $608 million. The plant's spent fuel rods are still stored in a facility on-site, because there is no permanent disposal repository to put them in. To monitor them and make sure the material does not fall into the hands of terrorists or spill into the nearby river costs $8 million per year.'