Feb 19, 2012

Sellafield faces nuclear option as overspending threatens plant's future - Environment - The Independent

Britain’s biggest single nuclear project has run into serious trouble with missed deadlines and cost overruns threatening the future of the entire nuclear reprocessing operation at Sellafield in Cumbria.

...The “evaporator D” project was originally estimated to cost £90m and was due to be completed as early as 2010. The Nuclear Decommissioning Authority, which has taken over responsibility for running Sellafield from the defunct British Nuclear Fuels Ltd, said that the actual costs are now estimated to be “around £400m” with a completion date no sooner than 2014.

Please continue reading at: