...alleged that NRC officials falsely invoked security concerns in redacting large portions of a report detailing the agency's preliminary investigation into the potential for dangerous and damaging flooding at U.S. nuclear power plants due to upstream dam failure.
Perkins, along with at least one other employee inside NRC, also an engineer, suggested that the real motive for redacting certain information was to prevent the public from learning the full extent of these vulnerabilities, and to obscure just how much the NRC has known about the problem, and for how long.
"What I've seen," Perkins said in a phone call, "is that the NRC is really struggling to come up with logic that allows this information to be withheld."
Please continue reading at: